Can I acquire land through squatters rights?
Most people are generally aware of the term “squatters rights” which in principle, allows a person who has been in possession of a piece of land for a long period of time to apply to acquire legal title to it. Given that this is a potentially lucrative endeavour for such a person, it is no surprise that the law surrounding it is complex and detailed.
The legal term for “squatters rights” is adverse possession and there are two separate regimes under the Land Registration Act 2002 which deal with such claims.
The first regime
In order to make an application for adverse possession of unregistered land or where the land was registered as at 13 October 2003 and there had been adverse possession for the appropriate limitation period by that date, it must be shown that:
1. The squatter has factual possession of the land
The question of whether a squatter has physical control of the land is a matter of fact and each case will be considered on its own merits. Broadly speaking however, evidence that shows that the squatter has used the land as an occupying owner might have been expected to deal with it will be compelling. Where land was previously open space, fencing is strong evidence of factual possession, but is not conclusive.
In a recent case in 2019, the court went even further when they decided that the act of laying paving slabs on the ground was sufficient to show physical possession of the land which gave the person the ability to be registered as the legal owner.
2. The squatter has the necessary intention to possess the land
The squatter must show that they intended to exclude the world at large from the land and possess it as their own. Most often, if factual possession has been established, the intention to possess the land will also be deduced from the same evidence, but not always.
3. The squatter’s possession is without the owner’s consent
Possession can never be adverse if the true paper owner has consented to the occupation, for example, under a lease or licence.
Each of the above factors must be shown to have been in existence continuously for a period of at least 12 years. The time limit is extended in certain circumstances for example where the land is owned by a Government department or has vested in the Crown as bona vacantia.
The second regime
The Land Registration Act 2002 introduced a new regime which applies only to registered land and no longer allows a squatter to acquire land by virtue of a period of possession alone. A registered proprietor of land will be more likely to be able to prevent an application for adverse possession succeeding under this regime.
All three of the requirements detailed above are required to establish a claim for adverse possession under the second regime and must be demonstrated for a continuous period of at least 10 years.
Provided such conditions are satisfied an application may be submitted to the Land Registry. However, this is where the process differs as the Land Registry will give notice of the application to the registered proprietor of the land in question (and any other applicable interested party). The notice allows 65 working days for a response and gives the true owner the opportunity to object to the application or serve a counter-notice.
The application may be objected to on the basis that the squatter is not entitled to apply on the facts of the case, for example, they were occupying with the consent of the true owner. If the registrar considers that the objection is not groundless, they will notify the squatter and allow the parties to come to an agreement between themselves. If such an agreement cannot be reached, the matter is transferred to tribunal.
If the true owner serves a counter-notice, then unless the squatter has stated in their original application that they wish to rely on one of the three conditions under Schedule 6, paragraph 5 of the LRA 2002 (see below), the application will be automatically rejected.
Even if a counter-notice is served, the application can still succeed if one of the three conditions are met, being:
1. It would be unconscionable because of an equity by estoppel for the registered proprietor to seek to dispossess the squatter and the circumstances are such that the squatter ought to be registered as the proprietor. An example of this may be where the squatter has built on the land in the mistaken belief that they were the owner of it and the proprietor has knowingly acquiesced in their mistake.
2. The squatter is for some other reason entitled to be registered as the proprietor. For example, where the squatter is entitled to the land under the will or intestacy of the deceased proprietor.
3. The squatter has been in adverse possession of land adjacent to their own for at least 10 years under the mistaken but reasonable belief that they are the owner of it, the exact line of the boundary with this adjacent land has not been determined under section 60 of the LRA 2002 and the estate to which the application relates was registered more than a year prior to the date of the application. The most common example is where dividing walls or fences were erected in the wrong place.
If the squatter’s application was rejected but they remain in adverse possession for a further 2 years from the date of the rejection, they will be entitled to reapply and be registered as the proprietor (save for in exceptional circumstances).
The process and legal requirements vary depending entirely on the circumstances of each individual case. It is therefore essential that you seek legal advice to ensure the correct procedure is followed to maximise the chances of an adverse possession application being successful.
For any further information, please contact us.
This reflects the law at the date of publication and is written as a general guide. It does not contain definitive legal advice, which should be sought as appropriate in relation to a particular matter.

Sign up
Enter your email address for legal updates on Property & Construction Law.
Latest Articles & Legal Insights
New JCT forms of building contract, 2024 Editions expected soon
The JCT announced at an event on 16 June 2023 that new editions of its contracts will be published in 2024.
The CIJC Working Rule Agreement: An Overview
The CIJC Working Rule Agreement is an agreement that governs the terms and conditions of employment for certain construction workers where the employer chooses to incorporate them.
Development Finance – What are my Options?
The ability to successfully deliver a profitable development project depends on getting the right funding arrangements in place.
Pawtential breach of covenant?
Recent statistics show that approximately 62% of households in the UK own a domestic pet…
Option agreements and considerations for landowners
An option agreement is where a prospective buyer, in this case the developer, enters into an agreement with a landowner for the right to buy their land.
Do you have a Construction Contract?
The Construction Act imposes statutory implied terms into all construction contracts including payment terms and a right to adjudicate.
Top Legal Insights
Contract Law
Material Breach of Contract
What is a ‘material’ breach of contract by a party to a commercial contract? This is a critical issue regularly considered by the courts. What constitutes a material breach and what are the remedies?
Property Law
Commercial Lease: The Financial impact on Landlord and Tenant
Coronavirus (COVID-19) and the restrictions now in place to control its spread, are having a significant effect on many business sectors.
Divorce and Family Law
Divorce in Lockdown: Can I get some discreet legal advice?
We have spoken to clients who are unfortunately experiencing some family issues, and would like to obtain expert legal advice, yet don’t know how...
Land & Property Dispute
Restrictive Covenants – The Price of Modification
Having identified that your land is burdened by a restrictive covenant and for the purposes of this article the covenant in question will be that only one residential building can be erected on the land. What do you do next?
Award winning legal advice
Herrington Carmichael offers legal advice to UK and International businesses as well as individuals and families. Rated as a ‘Leading Firm 2023’ by the legal directory Legal 500 and listed in The Times ‘Best Law Firms 2023’. Herrington Carmichael has offices in London, Farnborough, Reading, and Ascot.








Email: info@herrington-carmichael.com
Farnborough
Brennan House, Farnborough Aerospace Centre Business Park, Farnborough, GU14 6XR
Reading (Appointment only)
The Abbey, Abbey Gardens, Abbey Street, Reading RG1 3BA
Ascot (Appointment only)
102, Berkshire House, 39-51 High Street, Ascot, Berkshire SL5 7HY
London (Appointment only)
60 St Martins Lane, Covent Garden, London WC2N 4JS
Privacy Policy | Legal Notices, T&Cs, Complaints Resolution | Cookies | Client Feedback | Diversity Data
Our Services
Corporate Lawyers
Commercial Lawyers
Commercial Property Lawyers
Conveyancing Solicitors
Dispute Resolution Lawyers
Divorce & Family Lawyers
Employment Lawyers
Immigration Law Services
Private Wealth & Inheritance Lawyers
Startups & New Business Lawyers
Please be aware that we have no plans to change our bank details. If you receive any indication that any of our bank details have changed please contact us before sending us any funds. We take no responsibility for monies you transfer into the wrong bank account.
© 2023 Herrington Carmichael LLP. Registered in England and Wales company number OC322293.
Herrington Carmichael LLP is authorised and regulated by the Solicitors Regulation Authority with registration number 446245.