An overview of Force Majeure clauses

Apr 28, 2020

What is a force majeure clause?

A force majeure clause typically excuses one or both parties from performance of the contract in some way following the occurrence of certain events. There is no set form of force majeure clause wording, so clauses must be considered on a case by case basis.

Their underlying principle is that, on the occurrence of certain events which are outside a party’s control, that party is entitled to suspend or delay performance of all or part of its obligations and is excused from liability in respect of such failure or delay.

Under an English law contract, parties will not generally be able to rely on force majeure unless the contract contains a force majeure clause, since English law has no general rule of force majeure.

When can you rely on force majeure?

If your contract contains an express force majeure clause and you are intending to rely on it, whether the event constitutes a force majeure event under the relevant contract will depend on the particular wording of the force majeure clause.

If you are seeking to rely on the force majeure clause, you will bear the burden of proof to prove the scope of the clause and demonstrate that the facts in question fall within that scope.

How do you trigger the force majeure clause?

Again, this depends on the wording of the clause in question. Typically a force majeure clause will include formalities that must be complied with.

Force majeure clauses typically contain a notice requirement to invoke them. Notice invoking the force majeure clause may need to be given in a particular way and / or within a particular time period.

Failure to adhere to the relevant requirements may result in the protections afforded by the force majeure clause being lost, and may consequently result in you being in breach of the agreement if you are unable to comply with your contractual obligations.

What are the consequences of triggering the force majeure clause?

This will depend on the wording of the relevant clause, but outcomes typically include:

The ability for affected party to suspend performance and be granted an extension of time for performance;

The affected party being excused from liability for non-performance and / or inadequate performance for a period of time;

An obligation on the affected party to mitigate the effects of the force majeure event;

The ability for the unaffected party to terminate the contract – often the termination right will arise if the non-performance continues for a prescribed period of time, but this is not always the case and in some cases the termination right will arise immediately.

Other considerations

As described above, one of the potential consequences of the triggering the force majeure clause is that it may entitle the unaffected party to terminate the contract. Therefore, you should carefully assess whether triggering the force majeure clause is the most favourable approach for you in the circumstances.

If an unexpected event occurs which has or is likely to affect contract performance, it does not automatically mean that the affected party should trigger the force majeure clause – careful consideration should first be given to the requirements of the contract and whether any other more preferable options may be available.

This will typically involve a review of the contract as a whole in order to ascertain what the contractual obligations actually are – for example, if timescales for delivery are expressed as being estimates only, it may not be necessary for the supplier to trigger the force majeure clause if supply disruption is experienced.

How can we help?

For strategic advice on commercial contracts and force majeure, please contact the commercial team at Herrington Carmichael LLP using the details provided below.

Please contact Mark Chapman on 01276 686 222

This reflects the law at the date of publication and is written as a general guide. It does not contain definitive legal advice, which should be sought as appropriate in relation to a particular matter. 

Mark Chapman

Mark Chapman

Partner, Corporate and Commercial Law

By Mark Chapman

Partner,  Corporate & Commercial Law

Categories

Quick links

Sign up

Enter your email address for legal updates on Corporate and Commercial law.

Please see our privacy policy regarding use of your data.


Latest Articles & Legal Insights

ECCTA: Changes to Companies House Fees

ECCTA: Changes to Companies House Fees

One of the hot topics of speculation surrounding the changes brought in by the act was talk of a significant increase to Companies House fees.

Red Flag Commercial Contracts Review

Red Flag Commercial Contracts Review

We understand the legal challenges that in-house lawyers face in ensuring alignment between legal advice and business objectives…

EIS – Considerations for an Investor

EIS – Considerations for an Investor

The Enterprise Investment Scheme (EIS) is a government program that helps fund early-stage companies and provides tax benefits to investors.

Sign up

Enter your email address for legal updates on Corporate and Commercial law.

Please see our privacy policy regarding use of your data.


Top Legal Insights

 

Contract Law

Material Breach of Contract

What is a ‘material’ breach of contract by a party to a commercial contract? This is a critical issue regularly considered by the courts. What constitutes a material breach and what are the remedies?

Property Law

Commercial Lease: The Financial impact on Landlord and Tenant

Coronavirus (COVID-19) and the restrictions now in place to control its spread, are having a significant effect on many business sectors.

Divorce and Family Law

Divorce in Lockdown: Can I get some discreet legal advice?

We have spoken to clients who are unfortunately experiencing some family issues, and would like to obtain expert legal advice, yet don’t know how...

Land & Property Dispute

Restrictive Covenants – The Price of Modification

Having identified that your land is burdened by a restrictive covenant and for the purposes of this article the covenant in question will be that only one residential building can be erected on the land. What do you do next?

Wills, Trusts and Probate

Why is having a will so important?

It is entirely up to you if and when you want to create a Will, but it is important to be aware of the consequences of not having a Will.

Award winning legal advice

Herrington Carmichael offers legal advice to UK and International businesses as well as individuals and families. Rated as a ‘Leading Firm 2024’ by the legal directory Legal 500 and listed in The Times ‘Best Law Firms 2023 & 2024’. Herrington Carmichael has offices in London, Farnborough, Reading, and Ascot.

London

60 St Martins Lane, Covent Garden, London, WC2N 4JS 

+44 (0) 203 755 0557

Camberley

Building 2  Watchmoor Park, Riverside Way, Camberley, Surrey. GU15 3YL

+44 (0)1276 686 222

Wokingham

Opening Soon

+44 (0)118 977 4045

info@herrington-carmichael.com

© 2020 Herrington Carmichael LLP. Registered in England and Wales company number OC322293.

Herrington Carmichael LLP is authorised and regulated by the Solicitors Regulation Authority.

Privacy   |   Terms and Conditions   |   Cookies   |   Client Feedback