Avoiding dirty tricks in contract negotiations

Sep 25, 2019

Businesses must exercise caution when negotiating new contracts, particularly on the issue of costs and pricing. If costs are misrepresented or over-estimated, there is a risk that the other party could rescind the contract and claim fraudulent misrepresentation, as a recent case illustrates.

What’s the background?
Following an outbreak of avian flu in the US when millions of birds had to be slaughtered, a US supplier of egg-based products needed new supplies of dried egg products and negotiated a contract with a Dutch supplier. The agreement was subject to the US regulatory authorities approval of the procedures in the Netherlands for the regulatory supervision of the egg business. Once approval was given, the price was renegotiated upwards because of the additional costs associated with complying with the US regulations.

However, the figures presented by the Dutch supplier were intended to be accepted by the US as a genuine estimate of costs, whereas the evidence showed the figures actually included “an element of profit or buffer”. Following an audit of the Dutch company’s production processes, the US Company decided that they did not comply with US regulations and rejected the Dutch Company’s products. The US company refused to accept further shipments and claimed (among other things) fraudulent misrepresentation.

The High Court ruled that the costs put forward by the supplier amounted to a negotiating tactic and was not a genuine estimate of its costs. On the evidence, the supplier knew it was not a genuine estimate but something said to bring about a renegotiation of the price. This amounted to fraudulent misrepresentation on the part of the Dutch company as to additional compliance costs – with the intention of persuading the US company to agree a price increase.

What does this mean?
When preparing and conducting contract negotiations, business must take care to ensure they provide genuine estimates of their costs where they are presented as such or are intimated to be so – or risk claims of misrepresentation. It is good practice to make sure you have evidence to support any cost estimates in case a dispute later arises.

If a business is found to have deployed negotiating tactics in the form of, for instance, misrepresenting their estimated costs, it risks losing the contract and facing a potentially significant damages claim. The ruling is an important lesson to take due care in contract negotiations and avoid any ‘dirty tricks’ to induce the other party into concluding a contract.

How can we help?
We advise businesses and entrepreneurs on their contractual arrangements and terms, and their rights and responsibilities to the other contractual parties. For strategic advice and representation on all your commercial arrangements, contact the expert commercial solicitors at Herrington Carmichael LLP as early as possible.

Please contact Mark Chapman on 01276 686222 and Cesare McArdle on 0118 977 4045.

1 BV Nederlandse Industrie Van Eiprodukten v Rembrandt Enterprises Inc [2018] EWHC 1857

This reflects the law at the date of publication and is written as a general guide. It does not contain definitive legal advice, which should be sought as appropriate in relation to a particular matter.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Top read insights in 2019

Commercial Law

Material Breach of Contract

What is a ‘material’ breach of contract by a party to a commercial contract? This is a critical issue regularly considered by the courts. What constitutes a material breach and what are the remedies?

Property Law

Purchasing Land - Option Agreements

A developer and a landowner can enter into an Option Agreement. What are the strategies that can be employed by both landowners and developers to assist in such land deals?

Divorce and Family Law

What are the Tax Implications of a Civil Partnership?

Is there a significant tax saving to be made by a couple who are married or in a civil partnership that cohabitating couples simply don’t qualify for?  

Private Client

Restrictive Covenants – The Price of Modification

Having identified that your land is burdened by a restrictive covenant and for the purposes of this article the covenant in question will be that only one residential building can be erected on the land. What do you do next?

Construction Contracts

Contracts – terms implied by common law 

Construction contracts contain more than just the express contractual terms agreed between the parties.

Awards / Accreditations

Legal 500 Lawyers
Accredited Conveyancing Lawyers
Accredited Immigration & Asylum Lawyers

Andrew Smith is SFE accredited*

London

Amadeus House, 27b Floral Street, London, WC2E 9DP.
+44 (0) 203 755 0557

Camberley

Building 9, Riverside Way, Watchmoor Park, Camberley, Surrey. GU15 3YL.
+44 (0)1276 686 222

Wokingham

27 Broad Street, Wokingham, Berkshire. RG40 1AU.
+44 (0)118 977 4045

info@herrington-carmichael.com

© 2019 Herrington Carmichael LLP. Registered in England and Wales company number OC322293.

Herrington Carmichael LLP is authorised and regulated by the Solicitors Regulation Authority.

Privacy   |   Terms and Conditions   |   Cookies   |   Client Feedback